Urban Regeneration
PIU/Min. Tourism
Project Identification100%
Loan Appraisal100%
Loan Financing100%
Implementation5%
Procurement20%
Legal40%
Current Blockers
- Finalize and approve procurement framework(1 month)
Budget Support
PIU
Project Identification100%
Loan Appraisal90%
Loan Financing50%
Implementation0%
Procurement0%
Legal50%
Current Blockers
- Receive loan terms from OPEC Fund(1 week)
QEH Upgrade
Ministry of Health and Wellness
Project Identification100%
Loan Appraisal75%
Loan Financing10%
Implementation0%
Procurement5%
Legal20%
Current Blockers
- Identify and engage new potential lender(10 months)
Scotland District Road and Bridge Rehabilitation Project
Ministry of Transport and Works
Project Identification100%
Loan Appraisal100%
Loan Financing100%
Implementation10%
Procurement60%
Legal80%
Current Blockers
- Agreement on rates with contractor(3 months)
- Approval for staff compound(2.5 months)
Air Navigation Services Facility Upgrade
Ministry of Tourism & Int'l Transport
Project Identification100%
Loan Appraisal80%
Loan Financing20%
Implementation0%
Procurement10%
Legal40%
Current Blockers
- Submit financing application to new lender(2 months)
Construction of Berth 6 (North Berth)
Ministry of Tourism & Int'l Transport
Project Identification100%
Loan Appraisal100%
Loan Financing100%
Implementation30%
Procurement90%
Legal100%
Current Blockers
- Catch up on marine construction schedule(Ongoing)
Sector Wide Approach Programme (SWAP)
Ministry of Transport and Works
Project Identification100%
Loan Appraisal100%
Loan Financing90%
Implementation15%
Procurement80%
Legal90%
Current Blockers
- Relocation of utility poles for Rock Dundo Road(2 months)
- Staffing for CAF project(1 month)
Kensington Oval Upgrading Project
Prime Minister's Office
Project Identification100%
Loan Appraisal100%
Loan Financing100%
Implementation70%
Procurement85%
Legal90%
Current Blockers
- Submit supplementary budget request(2 weeks)
- Complete temporary stands(1 week)
Airport Sustainability
GAIA
Project Identification100%
Loan Appraisal40%
Loan Financing10%
Implementation0%
Procurement10%
Legal20%
Current Blockers
- Submit updated feasibility study to lender(11 months)
Skills for the Future II: Digital Transformation for Inclusive and Quality Education
Ministry of Education
Project Identification100%
Loan Appraisal100%
Loan Financing75%
Implementation20%
Procurement30%
Legal80%
Current Blockers
- Ministry of Finance budget approval(2 months)
- Procurement timeline from Tenders Committee(1.5 months)
Hope Agricultural Training Institute (HATI)
Ministry of Education
Project Identification100%
Loan Appraisal100%
Loan Financing100%
Implementation40%
Procurement90%
Legal70%
Current Blockers
- Final approval of construction drawings(1 month)
National Tourism Program
Ministry of Tourism & Int'l Transport
Project Identification100%
Loan Appraisal100%
Loan Financing100%
Implementation10%
Procurement50%
Legal20%
Current Blockers
- Finalize lease arrangements for Museum(3 years)
- Relocation of MHLM items from site(3 years)
Redevelopment of Shallow Draught Marina
Ministry of Tourism & Int'l Transport
Project Identification100%
Loan Appraisal100%
Loan Financing100%
Implementation75%
Procurement95%
Legal90%
Current Blockers
- Relocate boat repair facility(2 weeks)
- Relocate final storage container(1 week)
Accelerated Mill & Pave Programme
Ministry of Transport and Works
Project Identification100%
Loan Appraisal100%
Loan Financing100%
Implementation96%
Procurement100%
Legal100%
Current Blockers
No pending issues.
New School Meals Centre
Ministry of Education
Project Identification100%
Loan Appraisal100%
Loan Financing100%
Implementation80%
Procurement95%
Legal20%
Current Blockers
- Finalizing draft contract addendum(12 months)
- Remedial work assessment for equipment(4 months)
Waste to Energy System
Ministry of Tourism & Int'l Transport
Project Identification100%
Loan Appraisal70%
Loan Financing30%
Implementation5%
Procurement40%
Legal50%
Current Blockers
- Provide updated financial plan to lender(5 months)
- EPC Contractor selection(2 months)
UWI Centre for Food Security and Entrepreneurship (Dukes Project)
Ministry of Education
Project Identification100%
Loan Appraisal90%
Loan Financing60%
Implementation50%
Procurement70%
Legal40%
Current Blockers
- Lender approval for project changes(3.5 months)
- Compliance review for building standards(2 months)
New Fire Service Station and Headquarters, The Pine
Ministry of Home Affairs
Project Identification100%
Loan Appraisal100%
Loan Financing100%
Implementation60%
Procurement80%
Legal90%
Current Blockers
- Materials shortage resolution(4 months)
- Noise complaint mediation(1 month)
Alma Parris Memorial Secondary School
Ministry of Education
Project Identification100%
Loan Appraisal100%
Loan Financing100%
Implementation100%
Procurement100%
Legal80%
Current Blockers
- Urgent structural repairs assessment(5 months)
- Budget allocation for repairs(2 months)
Electronic Vehicle Registration (EVR) System
Ministry of Transport and Works
Project Identification100%
Loan Appraisal100%
Loan Financing100%
Implementation90%
Procurement95%
Legal10%
Current Blockers
- Amendments to Road Traffic Act(2 years)
- Outstanding payment to consultant(6 months)
Barbados Fire Service New Mechanical Workshop
Ministry of Home Affairs
Project Identification100%
Loan Appraisal100%
Loan Financing100%
Implementation20%
Procurement50%
Legal50%
Current Blockers
- Cabinet approval for Phase 3(1.5 months)
- Revised Cabinet Paper submission(1 month)
National Signage and Street Infrastructure Project (NSSIP)
Ministry of Transport and Works
Project Identification100%
Loan Appraisal100%
Loan Financing100%
Implementation0%
Procurement40%
Legal100%
Current Blockers
- Tender revision for Special Tenders Committee(3 weeks)
Renovations to Buildings at the Government Industrial School, Dodds
Ministry of Home Affairs
Project Identification100%
Loan Appraisal100%
Loan Financing100%
Implementation20%
Procurement80%
Legal100%
Current Blockers
No pending issues.
Modernization of School Infrastructure
Ministry of Education
Project Identification100%
Loan Appraisal50%
Loan Financing10%
Implementation0%
Procurement25%
Legal50%
Current Blockers
- Funding approval for virement(1 month)
Baxter's Road Fish Fry Garden
Prime Minister's Office
Project Identification100%
Loan Appraisal90%
Loan Financing90%
Implementation0%
Procurement20%
Legal30%
Current Blockers
- Land acquisition from Ministry of Housing(11 months)
Implementation of a Barbados Port Community System (PCS) (Phase II)
Ministry of Tourism & Int'l Transport
Project Identification100%
Loan Appraisal100%
Loan Financing100%
Implementation45%
Procurement20%
Legal100%
Current Blockers
- Re-procurement of server hardware(2 months)
- Agency cooperation for data integration(Ongoing)
Development of Oistins
Prime Minister's Office
Project Identification90%
Loan Appraisal0%
Loan Financing0%
Implementation0%
Procurement15%
Legal20%
Current Blockers
- Re-tender RFP for development(3 months)