Capital Projects
Barbados Fire Service New Mechanical Workshop

Critical Issue

The project is at a standstill because Cabinet approval is required to proceed with Phase 3. The Ministry of Finance and Cabinet have requested updated quotations and a revised Cabinet Paper to consider approving the contract for the same contractor (CRS Building and Maintenance). This is a multi-step administrative bottleneck that is preventing the project from moving forward.

Estimated Cost

$7,463,876

Responsible Ministry

Ministry of Home Affairs

Executing Agency

Ministry of Home Affairs

Anticipated Dates

Start: N/A

Completion: N/A

Revised Dates

Start: N/A

Completion: N/A

Funding Sources

No funding sources defined.

Project Identification
Loan Appraisal
Loan Financing
Implementation of Loan
Procurement
Legal
Comments
Overall Progress
Project Identification0%
Loan Appraisal0%
Loan Financing0%
Implementation of Loan0%
Procurement0%
Legal0%